Stages and rules for the construction of a suburban house from Arbolit
To build a foundation for a house from a arbolite, a combined type of foundation is chosen.
During its construction, the plot was first leveled, all the necessary marking was made, after which the soil excavation to a depth of 600 mm was made on the entire plane of the future foundation. Next, a sand pillow was covered with a thickness of 400 mm and well tamped with a vibro -plate.
After the formwork was mounted for pouring a monolithic reinforced tape, using a trimmed board, 40 mm thick.
After flooded concrete is strong, the formwork was removed. Then they made waterproofing from the internal as well as the outer sides of the foundation tape. Fortunately, now in the construction market to buy waterproofing materials for walls and foundations is no complexity. The sand was covered in the inside of the foundation tape and tamped in such a way that the sand pillow was flush with the upper edge of the tape foundation.
On the outer edge of the foundation tape, using a mantry solution, blocks of arbolite, size of 200x150x500 mm were laid so that they occupy half the upper site of the foundation tape.
A layer of waterproofing was laid on the inner plane of the foundation and on the sand, which completely closed the entire plane of the foundation and cavities with compacted sand. A monolithic reinforced slab was laid for waterproofing and a filled cage and flooded.
As a result of everything, all the advantages of the plate structure are combined in this foundation and a high base of the building is also made. At the same time, the monolithic stove of the foundation is also a reliable basis for the floor of the first floor of our building.